A deepwater operator in the Gulf of Mexico planned a well with 2.5° build-up rate (BUR) to reach geological targets and avoid nearby wells. In the build section of the well, the operator also needed to remove the remaining pilot hole so that casing could reach an optimum depth between a sand formation and a deeper slump with unknown depth spacing.

In similar hole sections, the operator had to perform a dedicated reaming run to open the remaining pilot hole. This required a trip with a new bottomhole assembly (BHA) that resulted in at least 30 hours of rig time for each well, increased health, safety, and environmental risks, and triggered hole condition issues.

Tool damage, system failures, and circulation loss in these wells pushed the operator to develop a 12-day authorization for expenditure (AFE) plan for the next well. Baker Hughes, a GE company (BHGE), combined several of its technologies to deliver precise directional control, overcome tool damage and failures, and eliminate the pilot hole for the next run. The AutoTrak™ G3 integrated rotary steerable drilling system (RSS) was deployed to provide reliable, precise steering of the BHA; the CoPilot™ measurement-while-drilling (MWD) monitoring system worked with the AutoTrak G3 RSS to provide smooth BUR; the ZoneTrak G™ near-bit gamma service identified the last sand formation; and the near-bit GaugePro™ Echo Series 14 on-command digital reamer with StaySharp™ cutter technology improved ROP and enabled the pilot hole to be efficiently reamed in the same run.

Download the PDF to read the full case study.

Challenges & Results
X

Challenges

  • Drill and clean entire section, including pilot hole, in one run
  • Minimize NPT and damage to downhole tools
  • Build inclination from 29° to 47° at BUR of 2.5°/100 ft (30.5 m)
  • Set casing between a sand zone and a slump zone

Results

  • Under reamed 124 ft (38 m) of pilot hole in one hour and eliminated a dedicated reaming trip, saving 30 hours of expected rig time
  • Achieved minimum BUR of 2.5°/100 ft (30.5 m)
  • Recorded no downtime or tool failures, reducing 12-day AFE plan by 50%